Construction Schedule

Day 1- Friday Oct 22nd (Door Knock Day)
A C T I V I T Y Start Time  Finish Time  Duration
Plans Stamped, All Permits Pulled DONE   N/A
Builders meet crew at Crowne Plaza 6:45 AM 7:30 AM  
AMBUSH OFFSITE 10:00 AM 2:00 PM 4 HR
Braveheart Ambush Check-in * subject to change 10:00 AM 11:00 AM 1 HR
BRAVEHEART AMBUSH  * TBD 11:00AM 1:00 PM 2 HR
Staging Set up 11:00 AM On going N/A
Check-in Set up 11:00 AM On going N/A
Deliver Storage Bins 11:00 AM 11:30 AM .5 HR
Deliver Framing package to staging 12:00 PM 1:30 PM 1.5 HR
Deliver United Rentals Equipment 12:00 PM 1:30 PM 1.5 HR
Mark power lines, underground utilites 12:00 PM 1:00 PM 1 HR
Deliver Demo/Excavation Equipment 12:00 PM 1:00 PM 1 HR
Site Meeting- All PROJECT MANAGERS 1:00 PM 2:00 PM 1 HR
Builder Walkie Set up 2:30 PM 3:30 PM 1 HR
Deliver Dumpsters 4:00 PM 5:00 PM 1 HR
Salvage wood from ex. Chicken/rabbit pen 4:00PM 5:00 PM 2 HR
Remove & Relocate mulch 4:00PM 5:00 PM 1.0 HR
Remove & Relocate firewood 4:00PM 5:00 PM 1 HR
Remove ex. Fencing 4:00PM 5:00 PM 1 HR
Begin installation of tree house supports 4:00PM 12:00 AM 8 HR
Surveyor layout - House, Garage 4:30 PM 6:30 PM 2 HR
Stage light towers around site 5:00 PM 6:00 PM 1 HR
Deliver Builders RV's 5:00 PM 6:00 PM 1 HR
House Move out 5:00PM 7:00 PM 2 HR
Disconnect Utilities  6:00 PM 7:00 PM 1 HR
Tree Removal  6:00PM 8:00 PM 2 HR
Out Building Demo 8:00 PM 10:00 PM 2 HR
Drop gravel for new drive 8:00 PM 9:00 PM 1 HR
Site Drainage 8:00 PM 1:00 AM 5 HR
Cut New Drive/Circle drive 9:00PM 11:00 PM 2 HR
Locate, pump and abandon septic tank/pipe 10:00 PM 11:00 PM 1 HR
Excavate for retaining walls/ house slab & footer 10:00PM 3:00 AM 5 HR
Prep pad for new foundation- Main house 10:00PM 3:00 AM 5 HR
Prep pad for new foundation- Garage/Gym 10:00PM 3:00 AM 5 HR
Surveyor to pin slab/ set elevations 10:00 PM 3:00 AM 6 HR
Deliver gravel into Garage/Gym pad 11:00 PM 3:00 AM 4 HR
gravel delivery-Haulers 11:00 PM 3:00 AM 4 HR
Day 2- Saturday Oct 23rd
A C T I V I T Y Start Time Finish Time  Duration
Place footers/place rebar/form slab-  Garage/Gym - Rigid Insulation Midnight 7:00 AM 7 HR
Deliver gravel into Garage/Gym pad 1:00 AM 3:00 AM .5 HR
Stage Pump trucks (2) 2:00 AM 3:00 AM 1 HR
Place and pour footers- Main house/porch/garage posts 3:00 AM 5:00 AM 2 HR
convey stone for retaining wall footer 3:00 AM 5:00 AM 2 HR
Slab Rough-in Plumber- Garage/Gym    3:30 AM 4:30 AM 1 HR
Footing/Foundation inspection- Garage/Gym 4:30 AM 5:00 AM .5 HR
Set House Foundation Forms 5:00 AM 7:00 AM 2 HR
Pour/Finish Foundation- Garage/Gym footings/slab 5:00 AM 9:00 AM 4 HR
stage retaining wall material 6:00 AM 7:00 AM 1 HR
gravel delivery for crawl- con't 6:00 AM 7:00 AM 2 HR
Footing/Foundation inspection- Main House 6:30 AM 7:00 AM .5 HR
convey gravel for crawlspace-con't 7:00 AM 8:00 AM 1 HR
Install retaining wall 7:00 AM 7:00 PM 12 HR
Trench electric underground/phone 7:00 AM 9:00 AM 2 HR
Install water, sewer, gas and elec to septic 7:00 AM 10:00 AM 3 HR
Pour House Foundation Forms 7:00 AM 9:00 AM 2 HR
All Concrete: cure time house/gym/garage 9:00 AM 3:00 PM 5 HR
Camera Demo/ Demo main house 9:00 AM 3:00 PM 6 HR
Set up Spider power boxes and run cable 3:00 PM 4:00 PM 1 HR
Stage Framing Materials- Garage/Gym 3:00 PM 4:00 PM 1 HR
Stage Framing Materials- House floor 3:00 PM 4:00 PM 1 HR
Stage Crane A - Steel Beam Delivery 3:00 PM 4:00 PM 1 HR
Strip forms- main house 3:00 PM 4:00 PM 1 HR
Rough in soil pipe below house/through foundation wall 3:00 PM 5:00 PM 2 HR
Snap out walls on slab- Garage/Gym 3:00 PM 4:00 PM 1 HR
Set posts/support for house tree feature 3:00 PM 4:00 PM 1 HR
waterproof foundation wall 3:00 PM 5:00 PM 2 HR
Set wall panels- Garage/Gym 4:00 PM 9:00 PM 5 HR
Set green plate, joists, and Advantech- House 4:00 PM 10:00PM 6 HR
Set deck/breezeway/garage porch posts 6:00PM 9:00 PM 3 HR
install septic field 7:00PM Midnight 5 HR
Backfill/Top dress site 7:00 PM 9:00 PM 2 HR
Stage trusses- Garage/Gym 7:00PM 8:00 PM 1 HR
Set trusses/Sheathing- Garage/Gym 8:00PM Midnight 4 HR
Stage Crane B 9:00PM 10:00 PM 1 HR
Snap out walls on deck- main house 9:00 PM 10:00 PM 1 HR
Stage wall panels- House 9:00 PM 10:00 PM 1 HR
Set First floor wall panels- main house 10:00PM 4:00 AM 6 HR
Day 3- Sunday Oct 24th
A C T I V I T Y Start Time Finish Time  Duration
Sheath Garage/Gym roof Midnight 4:00 AM 4 HR
Roof Install- Garage/Gym 2:00 AM 2:00 PM 12 HR
Stage trusses-House 4:00 AM 5:00 AM 1 HR
Set Roof Trusses/Sheath roof- House 5:00 AM Noon 7 HR
Begin deck install 5:00 AM 5:00PM 12 HR
Termite pretreat 6:00AM 8:00 AM 2 HR
Deliver Windows/Doors 6:00 AM 7:00 AM 1 HR
Hang Durock at chimney 7:00AM 9:00 AM 2 HR
Window/Door Install/ Interior Framing 7:00 AM 11:00 AM 4 HR
Stage interior tree feature 7:00 AM 8:00 AM 1 HR
Install interior tree feature 8:00 AM 10:00 AM 2 HR
Set log truss at front entry 10:00 AM Noon 2 HR
Design Producer Electrical Walk-Through  11:00 AM 12:00 PM 1 HR
Design Producer Low Voltage Walk-Through 11:00 AM 12:00 PM 1 HR
Energystar compliance work 11:00 AM 7:00 PM 8 HR
Rough-in Plumber    11:00 AM 7:00 PM 8 HR
Rough HVAC Start                11:00 AM 7:00 PM 8 HR
Rough-In Electric   Noon 8:00 PM 8 HR
Stage stone veneer, sand and mixers Noon 1:00 PM 1 HR
Pick up Framing/ Drywall nailers/ Deadwood/ Cornice Noon 8:00 PM 8 HR
Stage siding materials 1:00 PM 2:00 PM 1 HR
Install CMU blocks for stone @ column bases 1:00 PM 7:00 PM 6 HR
Exterior stone veneer 2:00 PM 2:00 PM 24 HR
Siding Install 2:00 PM 2:00 AM 12 HR
Stage roofing materials 2:00 PM 3:00 PM 1 HR
Design Producer Blocking Walk-Through 2:00 PM 3:00 PM 1 HR
Rough Phone/ Cable & Internet/ Security 3:00 PM 8:00 PM 5 HR
Roof Install- House 3:00 PM 3:00 AM 12 HR
Install Fireplace 4:00 PM 7:00 PM 3 HR
Framing inspection 6:00 PM 7:00 PM 1 HR
Rough electrical Inspection 6:00 PM 9:00 PM 1 HR
HVAC Inspection 6:00 PM 9:00 PM 1 HR
Plumbing  Inspection 6:00 PM 9:00 PM 1 HR
Measure for blinds 8:00 PM 10:00 PM 2 HR
Insulate Walls- Batts 8:00 PM 2:00 AM 6 HR
Day 4- Monday Oct 25th
A C T I V I T Y Start Time Finish Time  Duration
Insulation Inspection 1:00 AM 2:00 AM 1 HR
Energystar Inspection 1:00 AM 2:00 AM 1 HR
Clean site/house 2:00 AM 4:00 AM 2 HR
Permanent power 3:00 AM 6:00 AM 3 HR
Stage Dehumidifiers, Fans, Dryheat 4:00 AM 10:00 PM 18 HR
Load Drywall                                         4:00 AM 6:00 AM 2 HR
Hang, Tape, Sand, Fog Drywall 6:00 AM 9:00 PM 15 HR
Insulate crawlspace- Batts 8:00 AM Noon 4 HR
Install New Water Meter 8:00 AM 10:00 AM 2 HR
Pour front entry porch 8:00 AM 10:00 AM 2 HR
Pick up Framing/ Drywall nailers/ Deadwood, Finish Cornice 8:00 AM 10:00 PM 14 HR
Master Bath Shower mud pan Install 9:00 AM 1:00 PM 4 HR
Habitat to remove extra drywall material 6:00 PM 9:00 PM 3 HR
Measure for closet systems 8:00: PM 10:00 PM 2 HR
Design Producer Paint Walk-Through 8:00 PM 9:00 PM 1 HR
Prime/Custom colors interior of house 9:00 PM 3:00 AM 6 HR
Stage Interior Stone Material 9:00 PM 10:00 PM 1 HR
Design Producer Tile Walk-Through 9:00 PM 10:00PM 1 HR
Load Tile into House 9:00 PM 10:00 PM 1 HR
Tile install 10:00 PM 8:00 AM 10 HR
Install Fireplace surround/hearth 10:00 PM 4:00 AM 6 HR
Install Interior Stone 10:00 PM 2:00 PM 16 HR
Stage Soffit Material 10:00 PM 11:00 PM 1 HR
Soffit install 11:00 PM 11:00 AM 12 HR
Stage Interior Trim 10:00 PM 11:00 PM 1 HR
Load Interior cabinets                                11:00 PM Midnight 1 HR
Trim-Door Install 11:00 PM 8:00 AM 9 HR
Day 5- Tuesday Oct 26th
A C T I V I T Y Start Time Finish Time  Duration
Cabinet Installation Midnight 7:00 AM 7 HR
Measure for Countertops 3:00 AM 4:00 AM 1 HR
Courtyard, Porch, and Garage porch prep, form, and Pour 3:00 AM 8:00 AM 5 HR
Paint Prep- caulk/fill 4:00 AM 7:00 AM 3 HR
Stage Interior Paint 4:00 AM 5:00 AM 1 HR
Paint interior Walls & Trim 6:00 AM Noon 6 HR
Install  Countertops 7:00 AM 9:00 AM 2 HR
Measure for mirrors and shower glass  7:00 AM 8:00 AM 1 HR
Final grade fill material 8:00 AM 9:00 AM 1 HR
Final Grade   9:00 AM Noon 3 HR
Back Splash install 9:00AM 12:00PM 3 HR
Start landscaping  Noon 2:00 PM 26 HR
Stage Wood floor 11:00 AM Noon 1 HR
Install septic tank Noon 4:00 PM 4 HR
Install irrigation Noon 7:00 PM 7 HR
Install Wood floor & shoe mould Noon 8:00 PM 8 HR
Stage All Kohler Bath Accessories in Bathrooms 2:30 PM 3:30 PM 1 HR
Design Producer Bath Accessories Walk-Through 3:30 PM 4:00 PM .5 HR
Install Door Hardware & Finish Trim 4:00 PM 7:00 PM 3 HR
Bath & toilet accessories 4:00 PM 7:00 PM 3 HR
Designer Mirror Walk-Through 4:00PM 5:00PM 1 HR
Install Garage Doors/ openers 5:00 PM 8:00 PM 3 HR
Install Mirrors, Shower Enc. 5:00 PM 10:00 PM 5 HR
Design Producer Lighting Walk-Through 5:00 PM 6:00 PM 1 HR
Install Closet Systems 5:00 PM 10:00PM 5 HR
Security Finish 6:00 PM 8:00 PM 2 HR
Install Low Voltage Trim, Final  6:00 PM 9:00 PM 3 HR
Install HVAC Trim, Final/ A.C. Install 6:00 PM 1:00 AM 7 HR
Install Plumbing Fixtures, Final 6:00 PM 1:00 AM 7 HR
Install Electrical Trim, Final 6:00 PM 1:00 AM 7 HR
Install Wallpaper 10:00 PM 9:00 AM 9 HR
Paint Murals 10:00 PM 9:00 AM 9 HR
Day 6- Wednesday Oct 27th  (Funiture Move-In/Key Hand Over Day)
A C T I V I T Y Start Time Finish Time  Duration
Blow-in  ceiling insulation 5:00 AM 9:00 AM 4 HR
Stage Appliances 5:00 AM 6:00 AM 1 HR
Stage gutters and downspouts 6:00 AM 7:00AM 1 HR
Install river rock for "dry creek" 6:00 AM 9:00 AM 3 HR
Low voltage Landscape Lighting 6:00 AM Noon 6 HR
Annuals & Planters 6:00 AM 9:00 AM 3 HR
Mulch 6:00 AM 10:00 AM 4 HR
Install Appliances 6:00 AM 10:00 AM 4 HR
Install fencing 6:00 AM Noon 6 HR
Final Drywall Touch Up  6:00 AM 10:00 AM 4 HR
Final Paint touchup Int/Ext 6:00 AM 11:00 AM 5 HR
Final Grade Clean up & Spread Black Dirt 6:00 AM 8:00 AM 2 HR
Tile T/U 6:00 AM 9:00 AM 3 HR
Flooring T/U 6:00 AM 9:00 AM 3 HR
Sod 6:00 AM 11:00 AM 5 HR
Trim work T/U 6:00 AM 10:00 AM 4 HR
Install gutters and downspouts 7:00 AM 11:00AM 1 HR
Final Clean / Clean Windows 8:00 AM 2:00 PM 6 HR
Final inspection 10:00 AM 11:00 AM 1 HR
Street Sweep 11:00 AM 1:00 PM 2 HR
Restricted Access Noon    
Punch List Items Noon    
Key turn over to Extreme! 2:00PM    
Designer Move-in 2:00 PM 2:00 PM 24 HR
Furniture Move-in 2:00 PM 4:00 PM 2 HR
Punch out and picture install 7:00 PM Midnight 5 HR
Electrical Design fixture install 7:00 PM 11:00 PM 4 HR
Cable Final install 7:00 PM 9:00 PM 2 HR
Plasma TV install 7:00 PM 11:00 PM 4 HR
Install Blinds 7:00 PM 11:00 PM 4 HR
Clean site/Staging 7:00PM 7:00AM 12 HR
Day 7- Thursday Oct 28th (Reveal Day)
A C T I V I T Y Start Time Finish Time  Duration
5 Painters 6:00 AM 1:00 PM 7 HR
6 Trim carpenters 7:00 AM 11:00 AM 5 HR
Move materials and  clean site 8:00 AM 1:00 PM 5 HR
Fire Company for watering Lawn 8:00 AM 9:00 AM 1 HR
Final Glass cleaning 8:00 AM 11:00 AM 3 HR
Final / Final Clean 8:00 AM 2:00 PM 6 HR
2 Electricians 8:00 AM 1:00 PM 5 HR
2 Landscapers 8:00 AM 1:00 PM 5 HR
2 HVAC Techs 8:00 AM 1:00 PM 5 HR
2 Plumbers 8:00 AM 1:00 PM 5 HR
Street Sweep 8:00 AM 9:00 AM 1 HR
Clean Exterior Windows 9:00 AM Noon 3 HR
Move that bus! 2:00 PM    
Day 8- Friday Oct 29th (Wrap Day / Clean-Up Day)
A C T I V I T Y Start Time Finish Time  Duration
Clear materials from staging 9:00 AM 6:00 PM 9 HR
Initial Equipment Pickup 9:00AM 11:00 AM 2 HR
Extra Materials to Habitat 9:00 AM 6:00 PM 9 HR
Press Conference 10:30 AM 12:30 PM 2 HR
Make Punch list 3:00 PM 6:00 PM 3 HR
Punch work 5:00 PM 8:00 PM 3 HR
Day 9- Saturday Oct 30th (Clean-Up / Punch Out Day)
A C T I V I T Y Start Time Finish Time  Duration
Clean up day 9:00 AM 4:00 PM 7 HR
Punch work 9:00 AM 4:00 PM 7 HR
Clear materials from staging 9:00 AM 4:00 PM 7 HR
Final Equipment Pickup 9:00 AM    

 